Free CISM Domain 2 Practice Questions with Answers

These five CISM Domain 2 questions are drawn from Auditor Path's bank. Each follows ISACA's item-writing style: a scenario, four plausible options and one BEST answer. Read the explanation even when you get it right — it names the judgment the exam is testing.

Domain 2, Information Security Risk Management, is 20% of the CISM exam.

Question 1: Risk Assessment and Analysis

An asset is valued at 100,000. A threat is expected to occur once every four years and would destroy 40% of the asset's value. What is the annualized loss expectancy (ALE)?

Answer: C. SLE = asset value × exposure factor = 100,000 × 0.4 = 40,000. ARO = 0.25. ALE = SLE × ARO = 10,000.

Exam mindset: Know the arithmetic of quantitative risk.

Question 2: Risk Monitoring and Reporting

The board has set a low risk appetite for customer data exposure. How is risk tolerance BEST described in this context?

Answer: B. Tolerance sets the thresholds around the appetite that trigger escalation, which is why KRIs are calibrated to it.

Exam mindset: Appetite sets the target; tolerance sets the limits.

Question 3: Vulnerability and Control Deficiency Analysis

A zero-day vulnerability with no available patch affects a critical internet-facing application. What should the information security manager do?

Answer: D. When no fix exists, risk is reduced by compensating controls and detection while the owner decides on further action.

Exam mindset: No patch does not mean no action.

Question 4: Emerging Risk and Threat Landscape

Ransomware groups increasingly steal data before encrypting it and threaten to publish it if the ransom is unpaid. How should the information security manager update the organization's ransomware risk assessment?

Answer: D. Data theft before encryption changes the impact profile from an availability event to a confidentiality and regulatory event. The assessment must reflect that recovery capability no longer caps the damage.

Exam mindset: New attacker tactics change impact, not just likelihood.

Question 5: Risk Treatment / Risk Response Options

A new data loss prevention control has just been implemented as part of a risk treatment plan. What should be done BEFORE the residual risk rating is lowered in the register?

Answer: D. Residual risk reflects controls as they actually perform. Testing effectiveness first prevents an overstated sense of protection.

Exam mindset: Verify, then credit the control.